Latest News

      See all latest news >

Rebuilding Iraq - Electricity - Iraqi Local Partners - BC  
 
BC was established by a group of well experienced senior engineers in power stations rehabilitation & maintenance. Most of them were working in power stations and have been in this field for not less than 20 years and executed many power stations projects starting from erection, commissioning, operation and rehabilitation. Our company is a private company and we are a joint venture with the Ministry of Industry represented by AL-Faris Company who has a share of 24%.

AL-Faris company represent our strategically support from the point of its heavy industrial equipment and our company considered as the technical hand to execute the site works of Al-Faris company and any other mechanical and electrical works a warded to our company.

Staff
Projects
Services

Back to Top

  

Staff

1. Engineer Basil Naji Mahmood, … Managing Director,
Power station specialist, experienced in power plants for more than 28 years.
2. Engineer Hazim Karim Khadum, … Projects Manager,
Control Specialists, experienced in control systems for more than 20 years In thermal and gas power station.
3. Engineer Hadeer Ahmed Mohammad … Technical Manager,
Mechanical engineer, experience boilers turbines and pumps in thermal and gas power stations for more than 20 years.
4. Mr. Issam Abdul Ghafour Younis,… Designing and Civil works Manager
Architect engineer 30 years experience.
5. Mr. Hatif Ahmed Mohamed, … Marketing Manager
(PhD/Canada) in Economics, experience for more than 20 years.
6. Engineer Adel M. Yousif, … Computer Dept. Manager
More than 15 years experience.
7. Engineer Ali A. Sami, … Electrical Engineer.
15 years experience in Substation & Electricity distribution network.

Back to Top

Projects

Rehabilitation of Unit No.1 in Al-Musaib Power Station (300 MW),
which includes: Boiler, Turbine, generator & all auxiliaries (Pumps, valves, Heat exchanger, tanks, water treatment plant, pipe lines…etc). Also the maintenance for the Sub-Station (indoor & Outdoor) of the unit in (all the Unit Transformers, C.Bs & checking all cables and wiring diagrams).

Rehabilitation of Unit No.2 in Al-Musaib Power Station (300 MW) which includes: Boiler, Turbine, generator & all auxiliaries (Pumps, valves, Heat exchanger, tanks, water treatment plant, pipe lines…etc). Also the maintenance for the Sub-Station (indoor & Outdoor) of the unit i.e. (all the Unit Transformes, C.Bs & checking all cables and wiring diagrams). Also the replacement of all the local control instruments & control panels with all cables & wirings then install a new instrumentation equipments & control panels with new cabling and wiring.

Execution of 400KV transmission lines.

Rehabilitation the fourth unit of Baghdad South Power Station (55MW).

Rehabilitation of (3) 80 Ton/h water tube boilers replacement of about 39000m of bank tubes, riser tubes, economizer tubes headers …etc.

Rehabilitation a 5 Ton/h boiler.

Rehabilitation of about 20 hospitals boilers of different capacities.

Rehabilitation of water- pumps of Baghdad Municipal Office.

Rehabilitation of the boiler of Al-Rasheed Hotel.

Rehabilitation of the following items in the posts and concrete frames factory:

• Reconditioning of three boilers, Designing and executing of the relatives control panels. Erection
• Reconditioning of 3-over head cranes, a 60 cubic meters/hour concrete patching plant, tubes and pumps located in the factory.

Rehabilitation of two boilers in Al-Qadisiya Company.

Manufacturing of 2 Ton/Hr boiler for Salfonic factory, 1996.

Manufacturing of (3) boilers 2 Ton/h each for three private soft drinks factories, 1999.

Manufacturing of 5 Ton/h boiler for pre cast concrete factory, 2000.

Manufacturing of 1 Ton/h boiler for Golden tomato paste.

Manufacturing of 1 Ton/h boilers for Ibin-Yoanis Company.

Consulting and supervision for the rehabilitation of petrochemical Company boiler in Basrah.

Supplying of many spare parts for boilers to Al-Faris Company.

Dismantling, transferring and re-constructing of 5 Ton/h boiler from Al-Rasheed factory to Al-Ma’moon factory for the state company of vegetable oil production.

Rehabilitation of boilers and turbines of thermal power units no.1,2,3 in Baghdad south power station also carrying out the maintenance for the generators and automatic control & protection systems for these units.

Rehabilitation of boilers and turbines of thermal power units no.3 in Dora power station.

A contract of complete assessment of 39 diesel generators of 2MW each has been carried out by our technical staff in Mosul.

Baghdad co. has been recently awarded a contract of erecting, installing and commissioning two gas units each 40MW in ALSAMAWA southern Iraq.

  

Back to Top

Services

1. Erection, Maintenance & rehabilitation of all parts of the Power Stations (Boiler, Turbine, Pumps, Heat exchangers, water pipes, steam pipes, N. Gas pipes, air pipes, fuel pipes lines generators, main switch board & control panel) also we can deal with the construction of all these parts according to the drawings, instruction & supervision of the supplying company.
2. Execution of indoor & outdoor electrical sub-stations.
3. Execution of networks transmission lines (33KV, 132KV & 400KV) with the suitable towers for each line, including all civil, mechanical & electrical works.
4. Manufacturing of control & power panels of different shapes & capacities.
5. Execution of all kinds of fuel & water tanks (i.e fixed or floating roofs fuel tanks) and different types and diameters of pipe lines for water fuel, N. Gas & Air (carbon steel pipes & St. Steel pipes).
6. Execute of small and large oil refineries.
7. Execute of water treatment units and plants. Manufacturing of a small fire tube boilers up to 20 Ton/h in capacity also manufacturing heat exchangers.
8. Maintenance & rehabilitation of Gas turbine units, also the construction of new units including the civil, Mechanical and electrical works with all auxiliaries.

 